Joint wastewater treatment facility

Type of Jurisdictions Involved

City
Village

 

Specific Jurisdictions Involved

  • City of Delafield,
  • Village of Hartland

 

County

Waukesha

 

Region

Southeastern

 

Type of Agreement

Shared governance agreement with municipalities serving on control commission

 

Implementation and Incubation

  • Estimated 18 months to approve the commission and three years to construct new wastewater treatment facility

 

Factors Involved

  • Village of Hartland informed that their existing wastewater facility lacked the capacity to adequately serve their community
  • Increase in pollution in nearby Lake Nagawicka as a result
  • High costs associated with constructing a new sewage treatment plant

 

Benefits

  • Increased capacity for wastewater treatment
  • Sharing of all capital costs associated with construction

 

Results

  • Commission figures out user fees for both communities; communities bill residents
  • Village and City split all expansions 50/50

 

Web Site

 

 

Project Contact

General Manager
Scott Luczak
(262) 646-4364 Ext. 2

 

Contact

 

 

Abstract

 

 

Agreement

 